
1. Case Overview
In connection with a real estate pre-sale contract, the plaintiff (the contracting purchaser) sought rescission of the contract against the defendants (the developer and the trust company), demanding the return of the down payment and penalty already paid. The plaintiff argued that, due to causes attributable to the defendants, occupancy was delayed by more than three months beyond the scheduled occupancy date set in the pre-sale contract, and that the plaintiff was therefore entitled to rescind the contract and to be repaid the down payment and penalty.
2. Key Issues and Response
The core issues of this case were as follows.
(1) Validity of the rescission: whether legitimate grounds existed for the plaintiff to rescind the contract.
(2) Occupancy delay and exercise of the right of rescission: whether the period exceeding the scheduled occupancy date set in the pre-sale contract met the requirements for exercising the right of rescission.
(3) Tender of performance: whether the right of rescission remained valid in a situation where the defendant, after a certain period, obtained the building's use approval and actual occupancy became possible.
Law Firm Insight, representing the defendants, after closely reviewing the legal requirements for rescission,
proved that the plaintiff's declaration of intent to rescind the contract was not legally valid.
It emphasized that, because the defendant had obtained use approval, the building had been duly completed, and the occupancy schedule had thereafter been announced to the contracting purchasers, including the plaintiff, the grounds for rescission had been extinguished.
Accordingly, it argued that no legal right existed for the plaintiff to rescind the contract, and that there was no basis for the return of the down payment and penalty.
3. Outcome and Significance
The court dismissed all of the plaintiff's claims and ordered the plaintiff to bear the litigation costs as well.
Through the victory in this case, Law Firm Insight clearly organized the legal requirements relating to rescission and established, as a matter of law, that an occupancy delay does not automatically lead to rescission of the contract.
This case is a representative success story showing that, in disputes relating to occupancy delays and contract rescission that may arise in real estate pre-sale contracts, appropriate legal response can protect the rights of the defendant.